PROJECT EXPERIENCE
CURRENT OR RECENT PROJECTS
Carolina Power & Light
ICTG Project
Rowan County, NC
This project includes a 500/23 kV substation with a 1000 MVA, 500/230 kV transformer bank, 230 kV ring bus, two 230 kV capacitors banks and a bundled 1590 kc-mil 230 kV transmission line (ultimately two 230 kV lines). The project also includes a 230 kV plant switchyard for three 200 MW gas fired turbine generators with provisions to expand to seven 200 MW generators.
Monroe Power Company
ICTG Project
Monroe, GA
UTEC provided design, engineering, and construction observation for a 230 kV switchyard and associated transmission lines for a 180 MW gas fired turbine generator. The project included a 230/13.8 kV, 217 MVA unit connected step-up transformer, generator iso-phase bus, a 25 MVA 230/4.16 kV auxiliary transformer, three 230 kV OCBs, rigid bus low profile substation design, two 230 kV transmission lines and associated protection and control equipment.
The project also included revenue metering, telemetry, and alarming using a PLC system accessed over an intranet using TCP/IP.
The project was completed and ready for synchronization seven months after award of the engineering contract
Design of a new 100 kV substation with two 15/20/25 MVA transformers, five 15 kV circuit breakers, circuits switches, low profile steel structures and related protection and control for the Commissioners of Public Works in Greenwood, SC.
Addition of 15/20/25 MVA transformer and one 23 kV circuit breaker to CP&L’s Florence, SC Mt. Hope 115 kV substation.
Addition of 15/20/25 MVA transformer and three 23 kV circuit breakers to CP&L’s Wrightsville Beach, NC 115 kV substation.
Addition of 15/20/25 MVA transformer and one 23 kV circuit breaker to CP&L’s Wendell, NC 230 kV substation. |