UTEC
 


UTILITY TECHNOLOGY


ENGINEERS - CONSULTANTS

  Generation  
   
 


CO2 Fire Protection
Cooling Radiators
Fuel Tank
 






PROJECT EXPERIENCE

9.125 kW mobile engine-generator for peak shaving generation for Seneca, SC.

9,000 kW permanent engine-generator peak shaving generation plant for Seneca, SC.

3,000 kW standby/peak shaving generation plant for the Newport News Department of Public Utilities.

2,000 kW standby/load management generation unit for the North Carolina Zoological Park.

1500 kW standby/load management generation unit for the Lake Greenwood Water Treatment Plant in Greenwood, SC.

250 kW standby/load management generation unit for the CPW Operations Center in Greenwood, SC.

1,250 kW load management/standby generation unit for Roanoke Chowan Hospital.

455 kW standby/load management generation unit for Cross Road Retirement Center.

6,400 kW peak shaving plant at the Gaffney Delivery Substation in Gaffney, SC.

2,735 kW standby/peak shaving plant at the Gaffney Water Treatment Plant in Gaffney, SC.

1,600 kW standby/load management plant at the Clary Wastewater Treatment Plant in Gaffney, SC.

545 kW standby/load management facilities at the People's Creek Wastewater Treatment Plant in Gaffney, SC.

250 kW standby/load management facilities at the Operations Center in Gaffney, SC.



6,400 kW peak shaving plant at the
Gaffney Delivery Substation in
Gaffney, SC.
 

                                          



Switchgear at Gaffney 6400 kW Plant.

 

 

CURRENT OR RECENT PROJECTS

Seneca, SC

Installation of five (5) 1825 kW mobile diesel-engine generators to operate in parallel with the electric system over a one year period. UTEC is designing a permanent diesel-engine generating plant to be operational November 1, 2003. The plant capacity will be 9 MW.

Duke Solutions
Defense Supply Command

Richmond, VA

This project consisted of providing modifications required to place four existing 250 kW, 480 V diesel generators in parallel with the utility for load management parallel export of energy. Equipment at the site includes a 3750 kVA 480 V to 13.2 kV step-up transformer; 4000 A, 480 V bus duct; 4000 A, 480 V circuit breakers; and associated protection and control equipment. This project consisted of the protection and control design and protective relay settings for a 2 MW, 4.16 kV diesel generator operating in parallel with CP&L's 115 kV transmission system.